Explorer

WATCH: Visuals taken minutes after boiler explosion at NTPC plant in Raebareli's Unchahar

The NTPC management set up an enquiry to investigate the blast on November 1, when a boiler at 500 MW Unit-6 blew up and injured around 80 people.

New Delhi: The death toll in NTPC's Unchahar plant accident has climbed to 32, making it the country's worst industrial disaster in eight years, while the company said that investigations will be completed by an enquiry panel within a month. The accident is the worst since the 2009 collapse of a power-plant chimney under construction at Bharat Aluminium Korba project, which killed 45 people. The NTPC management set up an enquiry to investigate the blast on November 1, when a boiler at 500 MW Unit-6 blew up and injured around 80 people. "Around 80 people were affected due to this accident. 32 succumbed to injuries and 48 are under treatment," NTPC Chairman and Managing Director Gurdeep Singh told reporters here. As many as 12 seriously injured persons, including two with over 80 per cent burns, were air lifted and admitted to Safdarjung and Apollo hospitals in Delhi, he said. All possible measures are being taken to provide immediate relief to the families of the affected people in close coordination with the district administration, he added. Reasons for the NTPC blast Asked about the reasons for the blast, Singh said: "Enquiry will reveal whether it was human error, violation of safety norm or others. If I will tell you the reason then it would impose my view on the committee which will give its report in one month." The panel is headed by an NTPC Executive Director SK Roy and includes two general managers. Terming the boiler plant blast as "the rarest kind of incident", Singh said that people maintaining the unit were the most experienced. NTPC followed the laid down procedure to operationalise the plant and even the commissioning of the Unit-6 was delayed by six month, he said. The commercial date of operation was April this year as the company had achieved full load of plant (running at full capacity) in March itself, he added. The plant was declared commercially operational on September 30, 2017. About NTPC NTPC Ltd. (National Thermal Power Corporation Limited) is an Indian Public Sector Undertaking (PSU). It is engaged in the business of generation of electricity and allied activities. The headquarters of NTPC is situated at New Delhi. Company's core business is generation and sale of electricity to state-owned power distribution companies and State Electricity Boards in India.
View More
Advertisement
Advertisement
25°C
New Delhi
Rain: 100mm
Humidity: 97%
Wind: WNW 47km/h
See Today's Weather
powered by
Accu Weather
Advertisement

Top Headlines

Maharashtra: Sparks Fly In Mahayuti Over Leadership As CM Pick To Be Finalised Today — Updates
Maharashtra: Sparks Fly In Mahayuti Over Leadership As CM Pick To Be Finalised Today — Updates
PM Modi In Odisha Raises Alarm Over Cybercrime, Deepfakes; Urges Top Cops To Harness 'Double AI Power'
PM Modi In Odisha Raises Alarm Over Cybercrime, Deepfakes; Urges Top Cops To Harness 'Double AI Power'
Delhi's Air Quality Improves With First ‘Poor’ Category AQI In A Month, Experts Credit These Factors
Delhi's Air Quality Improves With First ‘Poor’ Category AQI In A Month, Experts Credit These Factors
AAP To Contest Delhi Elections Solo: Kejriwal Says 'There Won't Be Any Alliance'
AAP To Contest Delhi Elections Solo: Kejriwal Says 'There Won't Be Any Alliance'
Advertisement
ABP Premium

Videos

Campus Beats S4: Shantanu, Shruti & Sahaj Reveal Inside Gossips, Talk About Dance, Romance & MorePawan Singh's 'Sooryavansham' Shatters Records, Taking Bhojpuri Cinema to New Heights | ENT LivePowerStar Pawan Singh's Net Worth Revealed, A Look at His Luxurious Life and Crores in Wealth!Income Tax Strikes Hard on Tax Evaders in Major Black Money Crackdown | Paisa Live

Photo Gallery

Embed widget