Maruti Suzuki Targets 35% Vehicle Dispatches Via Rail By FY31

Maruti targets 35% vehicle dispatch via railways by 2030, up from 24% now. New Manesar rail hub to move 4.5L cars/year, saving 60M liters fuel.

Car market leader Maruti Suzuki India Ltd expects vehicle dispatches through railways to increase to 35 per cent by 2030-31, its Managing Director and CEO Hisashi Takeuchi said on Tuesday.

The company, which inaugurated its second automobile in-plant railway siding at its Manesar facility, has increased vehicle dispatches through railways, from just around 5 per cent in FY 2014-15 to 24 per cent last year, he said while addressing the event here.

The automobile in-plant railway siding at Manesar plant is India's largest GatiShakti multi-modal cargo terminal.

"Maruti Suzuki pioneered the use of railways for vehicle dispatches over a decade ago by becoming the first company to obtain the automobile-freight-train-operator license in India, and since then, we have dispatched over twenty-five lakh passenger vehicles using railways," Takeuchi said.

In March 2024, the automaker became the first automobile company to establish an in-plant railway siding in its Gujarat manufacturing plant.

"We have systematically increased vehicle dispatches through railways, from just around 5 per cent in FY 2014-15 to 24 per cent last year," he said.

Takeuchi said the company will take it further with the new facility at Manesar.

"Once it becomes fully operational, we will be able to dispatch 4.5 lakh vehicles annually, increasing the share of railway dispatches to 35 per cent by FY 2030-31," he added.

This means a growth of almost 40 per cent from the current level, Takeuchi said, adding "we will be able to avoid an estimated 1.75 lakh tonnes of carbon dioxide equivalent emission and save 60 million litres of fuel annually".

The Manesar railway siding, registered under the PM GatiShakti National Master Plan, has been developed as part of the 126 Km Haryana Orbital Rail Corridor (HORC) running from Sonipat to Palwal in Haryana.

Also Read : WhatsApp Breaks Its No-Ads Pledge: Status Screen To Get Advertisements. How They'll Work

The project has been executed by a joint venture firm Haryana Orbital Rail Corporation Ltd (HORCL).

Under the joint venture, MSIL has committed to invest Rs 325 crore in developing HORC.

Additionally, MSIL has invested about Rs 127 crore towards internal yard development, taking its overall investment to Rs 452 crore.

The railway siding at Manesar plant is spread over 46 acres inside the company's facility. It has a fully electrified corridor with four full-length tracks for rakes and one track for engine escape, totalling 8.2 kms of track length.

Models manufactured at MSIL's Gurugram and Manesar facilities will be dispatched to 17 hubs from this railway siding serving 380 cities across India, the company said.

Port locations of Mundra and Pipavav, used by the company for exports, will also be served, it added.

MSIL has dispatched 25 lakh vehicles cumulatively through railways since 2014-15. 

(This report has been published as part of the auto-generated syndicate wire feed. Apart from the headline, no editing has been done in the copy by ABP Live.) 

Top Headlines

N Chandrasekaran Resigns As Tata Sons Chairman Ahead Of August 18 AGM
N Chandrasekaran Resigns As Tata Sons Chairman: Here's What Happens Next
Molbio Diagnostics IPO Day 3: What Is The GMP Today? Check Before You Subscribe
Molbio Diagnostics IPO Day 3: Check GMP Before Subscribing, Issue Closes Today
Tata Sons Row Deepens: N Chandrasekaran May Step Down Ahead Of August 18 AGM Vote, Says Report
N Chandrasekaran May Quit Tata Sons Before AGM. Here's Why His Reappointment Is Uncertain
US-Iran Talks Stuck, Hormuz Fate Remains In Question: Sensex 100 Points Up, Nifty In Red
US-Iran Talks Stuck, Hormuz Fate Remains In Question: Sensex 100 Points Up, Nifty In Red

Videos

Jhansi Crash Mystery: Dashcam Footage Shows Aban Ahmed’s Creta Losing Control Before Fatal Impact
Rajya Sabha Uproar: Kiren Rijiju Seeks Chairman’s Intervention Amid Heated House Clash
IndiGo Emergency: Kolkata-Chennai Flight Lands Safely After Engine Fault Alert at Chennai Airport
Jhansi Crash Mystery Solved: Dashcam Footage Shows How Aban Ahmed’s Car Lost Control
Parliament Storm: Jharkhand Student Row Sparks BJP-Congress Clash as Lok Sabha Adjourned

Photo Gallery

25°C
New Delhi
Rain: 100mm
Humidity: 97%
Wind: WNW 47km/h
See Today's Weather
powered by
Accu Weather
Embed widget