431 Infra Projects Clock Cost Overrun Of Rs 4.80 Lakh Crore In Jan, 780 Projects Report Delays: MoSPI

The report found that out of 1,821 projects, 431 stated costs overrun and each of the delayed projects included an investment of Rs 150 crore or above

About 431 infrastructure projects were affected by cost overruns of over Rs 4.80 lakh crore in January 2024, an official report from the Ministry of Statistics and Programme Implementation (MoSPI) revealed. The report found that out of 1,821 projects, 431 stated cost overrun and each of the delayed projects included an investment of Rs 150 crore or above. About 780 projects were found to be delayed in the report.

The ministry oversees infrastructure projects including investments above Rs 150 crore, reported PTI. The original implementation cost of the 1,821 projects stood at Rs 26,09,679.38 crore, while the expected completion cost for the same stands around Rs 30,90,135.99 crore, marking an overall cost overrun of Rs 4,80,456.61 crore, the ministry said in its latest report for January 2024. These cost estimates stood higher by 18.41 per cent compared to the original costs.

The report also noted that expenditure for the projects till January 2024 stood at Rs 16,43,821.69 crore, representing about 53.20 per cent of the expected project costs. However, the ministry found that on calculating the delay on the basis of the latest completion schedule, the delayed projects decrease to 583.

For about 373 projects, the study found that the commissioning year along with the tentative gestation period remained unreported. From the 780 delayed projects, about 194 included overall delays in the range of 1-12 months, 187 projects were delayed for 13-24 months, 284 projects cited delays of 25-60 months, and 115 projects included delays of over 60 months. The average time overrun for the projects stood at 36.13 months.

Amongst the reasons cited for the delays, the report mentioned a delay in land acquisition, getting forest and environment clearances, and inadequate infrastructure support and linkages as the major factors explained by several project implementation agencies. Other factors like delays in tie-up for project financing, finalising detailed engineering, revisions in scope, tendering, equipment supply, and order, and law and order issues were also cited as responsible for the overruns. 

The report further noted that state-wise lockdowns owing to the COVID-19 pandemic also caused a delay in project implementation.

Also Read : Markets To Observe Foreign Fund Movements, Currency Fluctuations, Global Trends In The Week

Top Headlines

‘If You Misuse Your Visa...': US Embassy Warns B1/B2 Holders- Check Details
‘If You Misuse Your Visa...': US Embassy Warns B1/B2 Holders- Check Details
Turkman Gate Violence: Delhi Police On High Alert Ahead Of Jumma Namaz
Turkman Gate Violence: Delhi Police On High Alert Ahead Of Jumma Namaz
'Until Mamata Banerjee Arrived With Police…': ED Levels Serious Allegations, Moves High Court
'Until Mamata Banerjee Arrived With Police…': ED Levels Serious Allegations, Moves High Court
Greater Noida Residents Fall Ill After Consuming Contaminated Water: Reports
Greater Noida Residents Fall Ill After Consuming Contaminated Water: Reports

Videos

Breaking News: Maharashtra Politics Shifts: Congress Suspensions Boost BJP Ahead of Local Body Polls
Breaking News: Delhi Police Probe Reveals Social Media Role in Turkmen Gate Violence, YouTuber Salman Under Scanner
Breaking News: PM Modi Shares Pictures of Somnath Visit as ‘Somnath Swabhimaan Parv’ Begins
Breaking News: Inside Story of Turkmen Gate Bulldozer Action Near Faiz-e-Ilahi Mosque in Delhi
Breaking News: India’s GDP Expected to Grow at 7.4% This Fiscal Year, PM Modi Calls It Positive News

Photo Gallery

25°C
New Delhi
Rain: 100mm
Humidity: 97%
Wind: WNW 47km/h
See Today's Weather
powered by
Accu Weather
Embed widget