Govt Set To Blacklist Renewable Power Generation Companies For Delays: Report

To meet its goal of 500 gigawatts of renewable energy generation capacity by 2030, India has to install more than 40 gigawatts of capacity each year

The Central government will blacklist renewable power companies if they do not meet project completion deadlines, according to a report by Reuters. The report cites an order issued by the Ministry of New and Renewable Energy saying, blacklisting will be for a period of three to five years. 

"If any renewable energy project is not completed by the prescribed date of completion, then its bank guarantee should be encashed and the developer blacklisted after asking to show cause," the order issued on Wednesday said.

However, the report says India has not blacklisted any company from renewable energy generation contracts for delays so far. The blacklisting will be done in accordance with the government's General Financial Rules and would apply to all tenders.

To meet its goal of 500 gigawatts of renewable energy generation capacity by 2030, India has to install more than 40 gigawatts of capacity each year, the report said, adding that the installed base of renewable energy in the nation is close to 175 gigawatts. Due to equipment supply problems brought on by high import levies on solar equipment, the rate of installation is currently less than 15 gigawatts per year.

Also Read: Govt Likely To Continue With Wheat Export Curbs Amid Elections: Report

The ministry issued multiple extensions to a few projects due to the pandemic, the most recent of which was an order in December 2022 that extended the project's completion date by one year, to March 2024.

In Budget 2023, Finance minister Nirmala Sitharaman announced several schemes related to green energy generation. 

The finance minister said, “This Budget provides Rs 35,000 crore for priority capital investments towards energy transition and net zero objectives, and energy security by the Ministry of Petroleum and Natural Gas.” 

“The Inter-state transmission system for evacuation and grid integration of 13 GW renewable energy from Ladakh will be constructed with investment of Rs 20,700 crore including central support of Rs 8,300 crore,” she added.  

View More
Advertisement
Advertisement
25°C
New Delhi
Rain: 100mm
Humidity: 97%
Wind: WNW 47km/h
See Today's Weather
powered by
Accu Weather
Advertisement

Top Headlines

Parbhani Violence: Rahul Gandhi To Meet Victims’ Families On Monday, BJP Labels It As 'Drama'
Parbhani Violence: Rahul Gandhi To Meet Victims’ Families On Monday, BJP Labels It As 'Drama'
PM Modi Receives Kuwait's Highest Honour 'The Order Of Mubarak Al Kabeer'
PM Modi Receives Kuwait's Highest Honour 'The Order Of Mubarak Al Kabeer'
Epigamia Co-Founder, Rohan Mirchandani, Passes Away From Cardiac Arrest: Report
Epigamia Co-Founder, Rohan Mirchandani, Passes Away From Cardiac Arrest: Report
After Shah's Remark Triggers Speculation, BJP's Samrat Choudhary Clarifies On Nitish Kumar's Role For Bihar Poll
After Shah's Remark Triggers Speculation, BJP Leader Clarifies On Nitish's Role For Bihar Poll
Advertisement
ABP Premium

Videos

Mamata Machinery IPO Opens for Subscription, Closes on Dec 23, Expected Listing on Dec 27Complete Farmer Registry Update by Dec 31 to Receive PM Kisan 9th InstallmentWoman Dies in Mohali Building Collapse, Rescue Operations UnderwayHuge Black Money Seized in Madhya Pradesh Lokayukta Raids, Over Rs 7.98 Crore Discovered

Photo Gallery

Embed widget