Agra Metro Rail Project Picks Momentum Despite Covid Alarm

Of the total 686 piles, 400 for the 3 km elevated section of priority corridor from Taj East Gate to Jama Masjid have been completed till date.

Agra: While the city and its vast rural hinterland continue to reel under Covid-19 with alarming rise in the number of fresh cases in the past 20 days, construction work on the Agra Metro Rail project continues at a brisk pace.

The momentum has been maintained largely due to extensive arrangements made for prompt medical care to the large work force at the sites.

ALSO READ: Pappu Yadav 'Arrested' For Flouting Covid-19 Lockdown Rules Repeatedly

Groups of 15 have been formed to work in a coordinated manner, avoiding proximity.

Officials at the sites said, provision had been made for gloves, masks and shields. Thermal screening and continuous monitoring of health parameters have been ensured and all workers made aware of the gravity of the pandemic. A doctor and a nurse have been stationed at the casting site just in case any labourer needs medical attention.

In a record five month period 400 piles have been completed.

"It has been five months since December 7, 2020 when Agra Metro construction work was inaugurated by Prime Minister Narendra Modi. During this entire period Agra Metro has achieved fast progress and several milestones in the civil construction work of Agra Metro," an official said.

Of the total 686 piles, 400 for the 3 km elevated section of priority corridor from Taj East Gate to Jama Masjid have been completed till date. Along with this, 45 pile caps and 16 piers have also been completed for this section from Taj east gate to Fatehabad road.

The Managing Director, UPMRC Kumar Keshav said, "Vigour and Enthusiasm of UPMRC team is unbeatable. Agra Metro has achieved completion of 400 piles today in spite of all odds. Congratulations to team of Engineers of UPMRC, who have made this possible with there efforts."

It is to be noted that Agra Metro Project's civil construction work is going on for Priority section of first corridor, which runs from Taj East Gate to Sikandara. The priority section is a 6 km stretch from Taj East Gate to Jama Masjid, which comprises of 3 km elevated and 3 km underground section.


Top Headlines

SP, Congress 'Fond Of Graveyards': Adityanath Accuses Opposition Of Insulting Sanatan Dharma
SP, Congress 'Fond Of Graveyards': Adityanath Accuses Opposition Of Insulting Sanatan Dharma
'Mother Is Ex-IAS Officer': Kanpur Man Drags Girlfriend Out Of Car, Hits With Brick After Argument
'Mother Is Ex-IAS Officer': Kanpur Man Drags Girlfriend Out Of Car, Hits With Brick
Who Could Succeed Champat Rai At Ram Temple Trust? Top Contenders Emerge Ahead Of Key Meeting
Who Could Succeed Champat Rai At Ram Temple Trust? Top Contenders Emerge Ahead Of Key Meeting
Yogi Adityanath Slams Samajwadi Party, Claims UP Had Funds But No Vision Before 2017
Yogi Adityanath Slams Samajwadi Party, Claims UP Had Funds But No Vision Before 2017

Videos

GHAZIABAD RAIN HAVOC: Fallen tree, flooded roads and traffic chaos in Indirapuram
Jammu and Kashmir: Vaishno Devi Yatra Route Hit By Landslide Amid Heavy Rain, Battery Car Service Suspended
GHAZIABAD FLOOD FURY: Roads submerged, trees collapse, vehicles stranded
BREAKING NEWS: Monsoon Fury Grips Delhi-NCR, Roads Turn Into Lakes
Monsoon Crisis Deepens: Flood Alerts in J&K, Mumbai and Delhi-NCR Face Waterlogging

Photo Gallery

25°C
New Delhi
Rain: 100mm
Humidity: 97%
Wind: WNW 47km/h
See Today's Weather
powered by
Accu Weather
Embed widget